Carney have been instructed to complete works on a 21 day shutdown at the FCC Environment Waste plant in Allington, Maidstone, Kent. A description of the works and challenges are as follows:

  • Erecting scaffolding in vertical passes, Rowitec Furnace, Screw chambers, Hoppers and horizontal bridges.
  • Designs have been required due to specialist nature of works outside of simple TG20 requirements.
  • Works managed by Contracts Manager Steve Garner on 12 hr shift patterns to ensure speed and safety at all times.
  • Confined space jurisdiction has been managed onsite with permitted systems monitored throughout.