The principal contractor BAM Nuttall requested a speedy response over the Christmas of 2011 Carney Construction was responsible for construction of the new bridge structure at cow lane.

Completed over 5 days the timelapse video shows the influx of activity through the job, working safely to deadline to allow the entire replacement for added capacity of this aging railway bridge.

Construction of the bridge structure was completed offline to reduce disruption to railway before being lifted into position and tying in with remaining railway line.