During this contract Carney Construction supplied management systems, men & shuttering materials to Birse for this project in Pangbourne. This was used to form the replacement bridge deck & concrete abutments to the main bridge through Pangbourne.

Key Points:

  • Bridge deck poured in 3 full length strips 84m long to prevent deflections over supports (zero perpendicular construction joints).
  • Site flooded for 6 months, adjusted program & key dates all met
  • Zero reportable incidents
  • Using traditional timber shutters & GRP permanent formwork panels
  • Safe edge systems installed for working over the river Thames.
  • Additional packages – brickwork & scaffolding awarded onsite.